Here is your Alder/Poplar Reconstruction Project Update for the week of February 20-24
The weather last week prevented certain types of work, but crews were still busy getting things done:
• Concrete pad poured for the Library Book Drop
• Rebar cages set for Portland Cement Concrete (PCC) pavement on Park and Alder
• General cleanup
If the weather cooperates this week, crews will pour more concrete at the Park/Alder roundabout and will begin striping the roundabouts and connecting roads on Palouse Street.